The crew’s response to the potentially dangerous situation was highly commendable; their alertness and quick action ultimately prevented the parting of mooring lines and potential further complications.
CHIRP wonders whether the charterer’s agent properly assessed the berth for suitability in the prevailing weather conditions? Unsafe berth claims go against the charterer, not the owner, so they should have a local agent on site to satisfy themselves that the berth was suitable and to raise concerns with the terminal’s operator.
The design of the mounting block on which the pairs of roller fairleads are mounted requires review. The 90-degree edges act as a blade on surging ropes. Naval architects are reminded that the edges of these should be considered during the design phase of a new vessel. By eliminating such hazards at this stage can significantly decrease the chances of lines abrading or parting during the vessel’s lifetime. OCIMF’s Mooring Equipment Guidelines (MEG4)[1] provide further guidance on the design and construction of the mooring system.
Properly installed moorings are not only essential for the safety of the crew but also for maintaining the ship’s structural integrity. The risks associated with inadequately installed moorings—including the potential for fatalities, injuries, damage, and increased costs—can be effectively minimised by giving importance to mooring design and construction quality.
Vessel owners remain responsible for maintenance in most cases, and they should ensure that such hidden hazards are removed as soon as possible, or at the latest, during the vessel’s next maintenance period.
[1] https://www.ocimf.org/publications/books/mooring-equipment-guidelines-meg4